When constructing a campaign timeline it is advantageous to do which of the following?
The multiple moving parts of a campaign make it impossible to create a functional timeline.
Make educated guesses and change the timeline as necessary.
Estimate due dates based on employee availability.
Work backwards using deadlines for deliverables that are already established.