When constructing a campaign timeline it is advantageous to do which of the following?

The multiple moving parts of a campaign make it impossible to create a functional timeline.

Make educated guesses and change the timeline as necessary.

Estimate due dates based on employee availability.

Work backwards using deadlines for deliverables that are already established.